Module 15 of 49 · Part 3 – Barrier essentials: F9/AS1 · About 10 minutes · Sources checked 17 November 2026
1200 mm sounds simple – until the ground starts to rise.
Measure the 1200 mm minimum barrier height correctly – from the outside ground, on slopes, and for boundary fences, mesh, pool walls and gates.
Read the module in the flip book below. The cover image is AI-generated and illustrative only. A short quiz is at the end of the module, with answers included.
On-screen flip book · 9 pages
Page 1 of 9
Key learning points
- The Code itself sets no number. Clause F9 requires barriers that restrict access by unsupervised children under 5 (F9.3.1). The heights come from the Acceptable Solution F9/AS1.
- 1200 mm minimum for a barrier not on a boundary, measured from the finished floor or ground level outside the barrier (F9/AS1 2.1.2).
- 1800 mm for a barrier on a property boundary, measured from the ground on the pool side (2.2.1(a)), and for mesh with 13–35 mm openings (2.1.5).
- Ground features or objects outside within 1200 mm of the top of the barrier can defeat it – Figure 2 of F9/AS1 shows how to check (2.1.6).
- 760 mm is the wall height for small heated pools using a cover under F9/AS2 (2.1.1).
Key terms
| Term | Meaning | Where |
|---|---|---|
| Acceptable Solution | A design that, if followed, must be accepted as complying with the Code. | Building Act s 19; F9/AS1 |
| Finished ground/floor level | The surface outside the barrier that a child stands on. | F9/AS1 2.1.2 |
| R1200 arc | 1200 mm radius from the top of the barrier used to check for climbing aids. | F9/AS1 Fig 2 |
| Small heated pool | A heated pool (such as a spa or hot tub) with a water surface area of 5 m² or less, designed for therapeutic or recreational use (Module 29). | Building Act s 7 |
Official references
| Document | Version | Used for |
|---|---|---|
| Building Code clause F9 (Building Regulations 1992, Sch 1) | Version as at 15 January 2026; captured 29 Oct 2026 | F9.2, F9.3 |
| MBIE Acceptable Solutions F9/AS1 & F9/AS2 | First Edition, effective 27 April 2017 (no amendments listed); captured 17 Nov 2026 | AS1 2.1–2.5, 3.1.1, Figure 2; AS2 1.0, 2.1 |
Please read first. This guide is general information for learning only. It is not formal engineering, legal or compliance approval. Always check requirements with your Building Consent Authority or a qualified professional. Contact BlueHaven at support@bluehaven.nz.