Module 10 of 49 · Part 2 – Consents and planning · About 10 minutes · Sources checked 17 November 2026
Find the site’s hidden problems on paper, before you find them with a digger.
What a project information memorandum (PIM) tells you about a site, when you get one, and what goes into a pool building consent application.
Read the module in the flip book below. The cover image is AI-generated and illustrative only. A short quiz is at the end of the module, with answers included.
On-screen flip book · 9 pages
Page 1 of 9
Key learning points
- PIM = the council’s written summary of what it knows about the site that is relevant to your project – hazards, heritage, drains, other approvals.
- Optional in Auckland: an owner may apply (s 32). The BCA only applies for one automatically when it is not also the territorial authority (s 31(2)(a)) – and Auckland Council is both.
- Timing: a PIM is issued within 20 working days (s 34(1)(b)); the clock stops while the council waits for information it asked for.
- Consent application: prescribed form, plans and specifications (s 45). The BCA decides within 20 working days, paused by requests for information (s 48).
- For pools: Auckland’s AC1011 checklist has a whole pool and pool-fencing section, including the AC2344 producer statement cover sheet.
Key terms
| Term | Meaning | Where |
|---|---|---|
| PIM | Project information memorandum – site information relevant to proposed building work. | ss 31–35 |
| Special feature of the land | Includes potential natural hazards and likely hazardous contaminants. | s 35(2) |
| Working day | Any day except weekends, listed public holidays, the provincial anniversary day, and 20 December – 10 January. | s 7 |
| RFI | Request for further information – suspends the 20-day clock. | s 48(2) |
| AC1011 / AC2344 | Auckland Council residential lodgement checklist / pool barrier PS cover sheet. | Council forms |
Official references
| Document | Version | Used for |
|---|---|---|
| Building Act 2004, legislation.govt.nz | Version as at 8 Oct 2026 (re-checked 17 Nov 2026) | ss 31–35, 45, 48 |
| Auckland Council AC1011 Lodgement checklist – Residential | v.24, June 2026; downloaded 17 Nov 2026 | Pool section |
| Auckland Council AC2344 Producer statement cover sheet – pool fencing / barrier | v.1, June 2017; downloaded 17 Nov 2026 | Barrier PS cover sheet |
| Auckland Council, “Apply for a consent to put in a residential or small heated pool” | Captured 17 Nov 2026 | 20 working days; online only |
Please read first. This guide is general information for learning only. It is not formal engineering, legal or compliance approval. Always check requirements with your Building Consent Authority or a qualified professional. Contact BlueHaven at support@bluehaven.nz.