Module 13 of 49 · Part 2 – Consents and planning · About 11 minutes · Sources checked 17 November 2026
Digging the hole is permitted – until the site says otherwise.
Spot the Auckland Unitary Plan rules that can trigger a resource consent during the dig: earthworks thresholds, overlays, notable trees, flood plains and overland flow paths, and special character areas.
Read the module in the flip book below. The cover image is AI-generated and illustrative only. A short quiz is at the end of the module, with answers included.
On-screen flip book · 9 pages
Page 1 of 9
Key learning points
- Pool earthworks are permitted in every zone: AUP E12 Table E12.4.1 (A1) and E11 Table E11.4.1 (A1) list earthworks for installing swimming pools as P.
- Other site works aren’t automatic: regrading a garden is “general earthworks” – in residential zones, over 500 m² or over 250 m³ is restricted discretionary (RD).
- Overlays tighten things: in overlays the pool row is missing – new pool earthworks fall into “not otherwise listed”, with thresholds as low as 5 m² / 5 m³.
- General standards still apply to permitted earthworks – e.g. cleanfill only, limits on filling in flood plains, overland flow paths kept open.
- Trees, floods, character: work in a notable tree’s root zone (D13), structures in flood plains or overland flow paths (E36), and new buildings in Special Character Areas (D18) are RD.
Key terms
| Term | Meaning | Where |
|---|---|---|
| Land disturbance / earthworks | Altering land, e.g. excavation and filling. | AUP E11, E12 |
| Overlay | A mapped layer adding extra rules on top of the zone. | AUP Ch D |
| Protected root zone | Circle around a notable tree with radius = widest canopy reach. | AUP J1 |
| 1% AEP flood plain | Land expected to flood in a 1-in-100-year (1% annual chance) event. | AUP E36 |
| Overland flow path | Route surface water follows when pipes are full. | AUP E36 |
Official references
| Document | Version | Used for |
|---|---|---|
| AUP E12 Land disturbance – District | PDF footer “July 2026”; downloaded 17 Nov 2026 | Tables E12.4.1, E12.4.2; E12.6.2 |
| AUP E11 Land disturbance – Regional | PDF footer “July 2026”; downloaded 17 Nov 2026 | Table E11.4.1 (A1) (text only) |
| AUP D13 Notable Trees Overlay; J1 Definitions | PDF footer “July 2026”; downloaded 17 Nov 2026 | Table D13.4.1; protected root zone |
| AUP E36 Natural hazards and flooding | PDF footer “July 2026”; downloaded 17 Nov 2026 | Table E36.4.1 (A37)–(A42) |
| AUP D18 Special Character Areas Overlay | PDF footer “July 2026”; downloaded 17 Nov 2026 | Table D18.4.1 (A5) |
Please read first. This guide is general information for learning only. It is not formal engineering, legal or compliance approval. Always check requirements with your Building Consent Authority or a qualified professional. Contact BlueHaven at support@bluehaven.nz.